Up

 Click on the topic below to see further details. These are arranged in chronological order. Most of the pages contain a video viewer. If you are unable to use this to view the video clips, click on the direct video links just below the viewer to upload the .mpg file to your computer and view on whatever video platform your computer uses.

ASTRONOMICAL SKELETON CLOCK PROJECT, INDEX

Date

2003

Date

2015

  Pre-construction design work 01/15 Calendar, begin reversible, third-order perpetual calendar calculator complication  module
10-12/03 My early concept designs page 1 02/15 Calendar, complete the calendar calculator module
  2004-2006 03/15 Calendar remontoire and demonstration overdrive safety clutch
5/04 - 4/05 My early concept designs page 2 04/15 Calendar readout control levers, begin digital year indicator
4/04, 1/06 Buchanan's early concept designs 05/15 Calendar readout control levers and digital year indicator
  2006 06/15 Calendar, skeletonize calendar frames, other misc. items
Creation of working component models and first generation mockup 07/15 Calendar, completion. Begin tellurion module, design & wheel blanks
3/06 Working mockups in plastic - going barrel and planisphere 08/15 Tellurion assembly, frame blanks, spoke wheels
4/06 Working mockups in plastic - escapement and remontoire 09/15 Tellurion assembly, spoke and plant wheels
5/06 Fabricator's design drawings page 1 10/15 Tellurion assembly, skeletonized frames
5/06 Fabricator's design drawings page 2 11/15 Tellurion assembly, begin solar and lunar eclipse demo functions
01-06/06 Fabrication of full scale mockup 12/15 No work
7/06 Full scale mockup page 1   2016
7/06 Full scale mockup page 2 01/16 Tellurion assembly, sidereal, synodic month; solar, lunar horizons
7/06 Orrery mockup detail 02/16 Tellurion assembly complete. Complete sidereal dual dials

2007

03/16 Pendulum spring regulator assemblies
  Fabrication Begins 04/16 Pendulum spring, attachment parts
07-9/07 Main wheels, barrels & maintaining power systems 05/16 Escapement, start final finishing. Begin preparations for rating the clock
10-12/07 Time train, Wagner dual remontoire, wheels, differential drive 06-07/16 Escapement, final finishing, begin balance springs testing
08/16 Escapement, completion. continue balance springs testing
2008 09/16 Tellurion Earth globe, complete balance springs testing
01/08 Time train Wagner dual remontoire, output, cage, chaton assemblies 10/16 No work, My visit to the firm of Buchanan
02/08 Planisphere design work 11/16 Sun / Moon rise/ set module, dial design and development of first & second-order moon anomaly functions
03/08 Time train, continue wheel work 12/16 No work.
04/08 Time train, bevel wheels, fly design, columns, screws   2017
05/08 Time train, Wagner remontoire fly fabrication - rough out 01/17 Sun / Moon rise/ set, begin Great Anomaly & Projection variable differentials
06/08 Time train, Wagner remontoire fly fabrication - finish work 02/17 Sun / Moon rise/ set, complete variable differentials
07/08 Time train, assembly of fly to remontoire 03/17 Thermometer, analog
08/08 Escapement, antifriction wheel assembly, and main wheel clicks 04/17 Sun / Moon rise/ set, begin dial output drive assemblies
09/08 Escapement, antifriction wheel assembly, escapement wheels 05/17 Sun / Moon rise/ set, dial output drive assemblies and differential frame
10/08 Pendulum balance assemblies - arbors 06/17 Sun / Moon rise/ set, dial output drive assemblies, module frames, shutter cam rollers, differential setting & dials
11/08 Pendulum balance assemblies - antifriction wheels and their plates, complete arbors 07/17 Sun / Moon rise/ set dial output drive assemblies, sun drive center sector dials
08/17 Sun / Moon rise/ set, sun hand, glass dial work, redo center dial and bezel
11/08 Pendulum balance assemblies - begin balances 09/17 Sun / Moon rise/ set, finish sun hand, glass dial frame, shutter setting dial
12/08 Pendulum balance assemblies - complete balances 10/17 Sun/Moon rise/set; horizon shutter cams, movable dial plaques, mechanically complete
  2009 11/17 Sun/Moon rise/ set assembly, misc. work complete
01/09 Escapement pallets, grasshopper assemblies 12/17 No work.
02/09 Escapement pallets, grasshopper assemblies redesign   2018
03/09 Frames-entire compliment, complete redesign 01/18 Planisphere module mockup, miscellaneous projects
Remontoire fly fan decoration; time train clutch 02/18 Planisphere module, begin module
04/09 Remontoire components, refine. Seconds drive, begin celestial train 03/18 Planisphere module, continuation
05/09 Equation of time differential wheels, fly fan decoration, begin Robin remontoire 04/18 No work
06/09 Celestial train, continue Robin remontoire 05/18 Planisphere module, completion
07/09 Celestial train, continue Robin remontoire   Project to date photos
08/09 Celestial train, continue Robin remontoire 06/18 Orrery, begin preconstruction planning and design
09/09 Celestial train, finish Robin remontoire, Begin lower movement frame 07/18 Orrery, central support pillar, dial support bracket, begin Saturn gearbox
10/09 Frame-lower movement, completion. Bell strike hammer lift cams 08/18 Orrery, finish Saturn gearbox, begin Saturn armature drive wheel set
11/09 Bells; preparation for Horological Journal cover, Jan. 2010 09/18 Orrery, finish Saturn armature drive wheel set, begin Jupiter gearbox
12/09 Frame-upper movement, begin 10/18 Orrery, finish Jupiter gearbox, revise main orrery enamel dial ring
Project to date video page 11/18 Orrery, complete Jupiter armature drive wheel set
  2010 12/18 Orrery, begin inner planets gearbox
01/10 Frames/plates-upper movement roughs, stop work and power reserve indicators   2019
02/10 Stop work, cable hooks, begin power reserve indicators 01/19 January work combined into December 2018 installment
03/10 Power reserve indicators, barrel clicks, redesign 02/19 Orrery, continue inner planets gearbox
04/10 Power reserve indicators, complete; prep work upper frames 03/19 Orrery, continue inner planets gearbox
05/10 Frames-upper main, continue rough out, some finish & trim work 04/19 Orrery, complete inner planets gearbox, orrery mechanically complete
06/10 Frames-upper main, rough out complete, some finish & trim work 05/19 No work
07/10 Frames, going, celestial, equation trains and pendulum support fabricated 06/19 Orrery and other detail work
08/10 Demonstration clutch parts, project to date photos; films 07/19 Orrery, completion
09/10 Pendulum balance diagonals; poising weights, strike train rear frame   Project photos and video to date
10/10 Strike train snail transfer train 08/19 No work
11/10 Strike train Fasoldt epicyclical fly fans, begin 09/19 No work
12/10 Strike train fly fans. Begin strike/ repeat control assemblies 10/19 Spring drive from weight drive conversion, begin. Begin clock disassembly for final finishing of all components
  2011 11/19 Spring drive conversion complete, begin misc. fabrications, refining and finishing of all components for final reassembly
01/11 Strike and repeat control assemblies, schematics; rack mockups, 12/19 Base frame, strike flies, fabricate demo drive speed selector
02/11 Strike and repeat control assemblies, main strike fly fan detents   2020
03/11 Strike and repeat control assemblies, initiators 01/20 Time train finished, main frame wheel works and sidereal time complication
04/11 Strike and repeat control assemblies, complete initiators 02/20 Equation and time transfer trains, tripartite drive, escape wheel assembly, rack let-down flies, orrery drive, fabricate dial support latches
05/11 Strike and repeat control assemblies, continue main strike fly detents 03/20 Thermometer, demo drive crank and transfer wheels, begin strike train
06/11 Strike and repeat control assemblies, rack pawls; rack let down flies 04/20 Strike train, continue; begin celestial train
07/11 Strike and repeat control assemblies, quarter and hour racks 05/20 Celestial train, finish; finish strike train control lever work
  Project to date photos and video page 06/20-
07/20
Calendar module debugging and finishing, begin dial bezel work
  2012 08/20 Calendar module finished
8/11-9/12 Fourteen month hiatus for restoration of the Pouvillon clock 09/20 Tellurion finished, continue dial bezel work
10/12 Movement stand, inner steel structure 10/20 Planisphere mask, finish dial bezels, and misc. demonstration mechanics
11/12-5/13 Seven month hiatus for manufacturing facility relocation 11/20 Planisphere finished, begin Sun and Moon module, misc. setting dials
                                                                            2013 12/20 Sun and Moon module and orrery finished, enamel dial work installed                                 
  Fabrication of enamel dial work, compilation, Feb. 2008 - May 2013   2021
  Dial work -  Feb. 2008 to Jan. 2012, planisphere, main time dial 01/21 Clock frame, structural support sub base redesign, finish most dial hands
06/13 Dial work - Mar. 2012 - Aug. 2012, orrery, redo main time dial   Debugging begins and completion of the final phases of the project commences
  Dial work - Mar. 2012 - Aug. 2012, orrery, redo main time dial 02/21 Dial hands finished, sedan chair carry frame constructed, debugging begins
  Dial work - Dec. 2012 - May 2013, redo orrery, complete remaining dials 03/21 Demonstration selector retrofit - finished, debugging continues
07/13 Main frame cross pillars, replacements 04/21 Correction for seconds hand, design issue, debugging continues
08/13 Main frame cross pillars, replacements 05/21 Correction for seconds hand finished, world time dial corrected and finished, fabrication of case is finished, debugging continues
09/13 Demonstration drive, celestial train, the orrery dual speed transmission 06/21 Sub-base surround built, dedication plate, winding key reviewed, debugging continues
10/13 Demonstration drive transmission, begin orrery output gearing 07/21 Various small chores addressed, timing trials begin, debugging continues
11/13 Demonstration drive and orrery output gearing, completion 08/21 Various small chores addressed, timing trials continue, debugging continues
12/13 No work 09/21 Case arrives, keyways fabricated, custom table ordered, debugging continues
Date 2014 10/21 Wood sub base surround finished, final photography and videography finished, NAWCC Zoom presentation, debugging completed
01/14 Strike snails and begin strike hammer linkages 11/21 Correction of dual Wagner remontoire phasing
02/14 Strike hammer linkage, continue 12/21 The end of the original first and second generation mockups
03/14 Strike hammer linkages, completion   2022
04/14 Strike hammers 01,02/22 Rating of clock & miscellaneous
05/14 No work 03,04/22 Begin key set fabrication, fabricate shipping crates. custom display table arrives
06/14 No work 05/22 Finish key set fabrication, dedication plate
07/14 Strike and repeat selection levers, misc. parts, complete strike control system   The fabrication of the Astronomical skeleton clock is completed
08/14 No work 06/22 Preparing for shipping and the development of the Operations Manual
09/14 Sidereal, equation of time and calendar function drives 07/22 Arrival to the USA of the Astronomical skeleton clock, begin reassembly
10/14 Finish last month's work. Begin mockup for the perpetual calendar module 08/22 Complete reassembly, the project is finished
11/14 Sidereal, equation drives, kidney cam, equation of time system complete   I hope anyone who has followed this adventure has enjoyed it as much as I have!
12/14 Calendar, begin mockup for calendar remontoire, begin fabrication    
       
       
       

Free Website Hit Counter
Free website hit counter

Up